  Centre Place Retail & Office, Project No. Y09-005

Centre Place Retail & Office, Project No. Y09-005

South California Bl at Olympic Bl
(Same property as the KFC & Baja Fresh restaurants)



View from Olympic Bl at South California Bl

 ARCHITECT:  Peter Stackpole
LCA Architects
V:  (925) 944-1626
 
APPLICANT: 

Tom Miller
Hall Equities Group
V: (925) 933-4172

 STAFF: Ken Nodder, Sr. Planner
V: (925) 943-5899 x2234


Description:

Demolition is currently underway at South California Blvd. and Olympic Blvd. (near Alma Park) to make way for a new commercial development known as Centre Place. Hall Equities Group is redeveloping the two-acre commercial site currently known as California Plaza at 1231-1275 South California Boulevard. The project will include demolition of a 14,742 square-foot portion (~75%) of the existing one-story retail building (all but KFC/Baja Fresh), and construction of two new buildings totaling 17,707 square feet with retail, bank, and office uses at the north end of the site. Building #1 is a two-story, 13,157 square foot office/bank combination designed for a single tenant with the bank component on the first level and associated offices above. Building #2 is a one-story 4,550 square foot retail/restaurant building designed for one or more tenants.

Limited, additional work will include grading and re-landscaping within the City’s adjacent Alma Park. The developer will also enlarge, re-design, and re-landscape the entire Alma Park entryway plaza at the intersection of S. California and Olympic Boulevards. The plan includes new flat work with different paving materials and all new landscaping within a larger, more open plaza at the corner and possible artwork locations. Additional improvements include a wider throat within which a more linear, wider, and ADA accessible walkway would be created from the intersection up into the park. Park entrance improvements will include the removal of several mature pine trees.



History of Public Hearings and Public Meetings
 
Agendas, staff reports, attachments, and minutes for this project are available on the Archive Meetings & Minutes web page.  Select from the following commission archive dates below:

March 18, 2009

 Design Review Commission (DRC) Item 4b

April 7, 2009

 Park, Recreation, & Open Space Commission (PROS)
 May 4, 2009

 Park, Recreation, & Open Space Commission (PROS)

May 6, 2009

 Design Review Commission

May 28, 2009

 Planning Commission

June 4, 2009

 Planning Commission (Special Meeting)

June 16, 2009

 City Council

July 1, 2009

 Design Review Commission (Final Design Review) Approved